top of page

Milestones

Milestones: About Me

Risk Assessments and Training

Thursday 31st October 2019

Before any experimental work could be accomplished the team had to complete a detailed risk assessment and undergo rigorous training to safely operate the rig and the other heavy equipment required for the manufacturing of a panel. The training and risk assessment was completed later than had previously been scheduled due to conflicting time schedules and logistical difficulties.

Milestones: Welcome

First Run

Friday 1st November 2019

The team were eager to begin the experimental work as quickly as possible to achieve as much as possible before the end of the first semester. However, after a few hours of rig operation fibres stopped collecting and an unpleasant smell was noticed in in the operating room. The team immediately halted the operations and decided to leave the rig to cool down before investigating what had happened. On Monday the 3rd of November the team disassembled and cleaned the rig and discovered considerable blockage at the top of the reactor.

Blockage
Milestones: Welcome
Open LCA logo

Finding Software 

Tuesday 5th November 2019

Following research of possible LCA software to carry out the analysis, OpenLCA was chosen due to characteristics such as:

·         Opensource

·         User Interface

·         Postprocessing tools

·         Forum access

·         Documentation

To this point, research papers have been consulted to build a picture of the best way to approach the LCA, this will continue alongside study of the standards ISO 14040 and ISO 14044.

Milestones: About My Project

Thermal Cleaning Collected Fibres

Tuesday 11th November 2019 

Fibres that were collected from the rig had to undergo thermal cleaning to assure that the previous chemical sizing was removed from the fibre. Due to issues with the rig the collected fibres were considerably more charred than expected thus the thermal cleaning was used to remove the unburnt plastic as well. After the thermal cleaning the recycled fibres were combined with polypropylene to form a mat, four mats were required to create a panel.

Charred fibres
Cleaned fibres
Milestones: Gallery
First Panel

The First Panel

Monday 17th November 2019

The manufacture of the first panel took considerably more time than had previously been expected due to the complications that arose with collecting glass fibres from the rig. The first panel only underwent thermal cleaning as this would be used as a baseline to measure any improvements in the mechanical strength of the fibres with any extra treatments.

Milestones: Welcome

ITA, Aachen Samples

Monday 2nd December 2019

Dr Yang had received the samples from Aachen and after some analysis the group determined that the process looked very promising. However to achieve better results further analysis had to be conducted and so it was vital to send more recycled glass fibres and possibly even conduct a visit to learn more about the process and further investigate the possibilities of using this process to create GFRP using recycled glass fibres.

Aachen samples
Milestones: Welcome

Finalising LCA Plan

Wednesday 4th December

A plan of attack for LCA has been constructed which includes collaboration with the ACG in the University of Strathclyde. The collaboration will surround upscaling the rig to achieve accurate energy usage which can be used as an input for OpenLCA. An effective plan for LCA has been created which will be communicated to the group’s stakeholder in the coming weeks and make any changes prior to work commencing in semester 2.

Milestones: About My Project

Commercial Scale Rig Schematic

Commercial scale rig schematic
Milestones: Image
Tensile bars

Additional Panels

Monday 6th January 2020

The second semester started of very successfully, after some alterations to the rig a considerable amount of fibres was collected. During the week the rig was ran twice and enough fibres were collected to craft an additional three panels. The three new panels were all created with different treatments to investigate their effect on the fibre strength regeneration. A couple of weeks later, the panels were laser cut into tensile bars with the purpose of undergoing tensile testing to determine the optimal strength regeneration process for the recycled fibres.

Milestones: Welcome

Data Completion Breakthrough

Thursday 30th January

Data research for both shredding and transportation of the composite have been completed with effective progress of the rig with collaboration with the ACG. This sets the group up well for data research of the manufacturing processes including compression moulding, injection moulding and bulk moulding compounding.

Milestones: About My Project

Mechanical Testing

Friday 14th February

The final step after crafting a panel was to perform a tensile test on the five bars produced from each panel. The tensile test was performed in the laboratory at Strathclyde University where the equipment produced a stress-strain graph until fracture. This meant the fracture strength, ultimate tensile strength, Young's modulus and other useful properties could be determined.

86776579_2499055393689786_55915841212697
Milestones: Welcome

LCA Results

Friday 20th March

The team have completed all data entry to the software and obtained results for both energy usage and carbon emissions. The analysis is currently being undertaken with reference to ISO standards as well as technical research papers, this allows comparisons and effective conclusions to be drawn. The analysis will be completed next week to allow the group to put these into the report and effectively conclude the LCA study.

Milestones: About My Project

My Project

Group N are proud of their academic achievements and would like to share this with you, use the button below to view their final report.

Download Now
Milestones: My Work

MAE Final Year Project

16 Richmond St, Glasgow G1 1XQ

  • instagram

©2019 by Recycling End of Life Wind Turbine Blades. Proudly created with Wix.com

bottom of page